Brentford Footbridge Successfully Installed

HomeBlogNewsBrentford Footbridge Successfully Installed

Brentford Footbridge Successfully Installed

25 April 2023

The steel deck for a new active travel bridge at Brentford Lock West in West London was successfully installed last weekend using an 850 tonne capacity mobile crane.

The bridge spans the Grand Union Canal, landing in Canal Square on the southwest side, and in Robin Grove recreation ground on the north east side.

We have been involved with this bridge since we prepared concept designs in 2018 and then undertook the detailed design.  So it is great to see it nearing completion.